Greg Abbott Promised No Data Center Permits Until His Audit Was Done. Ten Days After He Lost, His Office Switched Them Back On — Weeks Before the Audit Is Due.

Abbott's office told Texas regulators on November 13 that his data center pause could end. The next business day they approved three gas plants big enough to power 875,000 homes, with no public notice — while the audit the pause was waiting on still isn't public, and its final report isn't due until December 10.

Greg Abbott Promised No Data Center Permits Until His Audit Was Done. Ten Days After He Lost, His Office Switched Them Back On — Weeks Before the Audit Is Due.
Photo: Getty Images, via FOX 7 Austin

In September, Greg Abbott told Texas's environmental agency to stop approving permits for data centers. He said the state needed answers first: whether these projects pay their own way, whether they bring their own water, and what they do to the people who live next door.

Ten days after Texas voters fired him, his office told the agency it could start again.

On Friday, November 13, the governor's office notified the Texas Commission on Environmental Quality that the state's grid operator, ERCOT, had finished gathering information on data centers. On Monday, November 16, the agency resumed approving permits. That same day it approved three gas-fired power plants built to run data centers.

The audit those permits were supposed to wait for still has not been made public. Its final report isn't due until December 10.

What Abbott promised

Abbott's September 21 order paused environmental permits for data centers over worries about electricity demand, water supplies and the effects on nearby residents. His directive said data centers must pay their own infrastructure costs and protect the water communities need.

The letter he sent the agency asked that no projects be approved until the audit was complete. After the review, he said, the agency should approve only audited data centers that followed his rules.

We already wrote about the problem with that schedule. Abbott announced the pause in an election year, and the audit's answers were set to arrive 37 days after Texans voted. Then watchdogs found his agency took 35 permitting actions for data centers during the "pause" anyway.

Now the pause is over, and it ended before the answers came in.

The audit isn't done

The state's story is that ERCOT finished collecting information. ERCOT heard back from 433 of the 465 projects it asked. Detailed analysis is still underway, and the final report is targeted for December 10.

That is weeks after permits started flowing again. As of FOX 7's reporting, ERCOT's findings had not been publicly released. According to the watchdog group Public Citizen, Politico reported that ERCOT said it was still working to complete the audit. Neither the agency nor the governor's office posted a public notice that the pause had ended.

So the pause Abbott said would protect Texans ended before anyone could see what the audit found. The public still hasn't seen it.

What got approved

Public Citizen tracked what happened the day permitting restarted:

  • Three data center gas plants approved in one day, with a combined capacity of 3,500 megawatts. That is enough to serve roughly 875,000 Texas homes at peak hours.
  • No public notice and no comment period. All three went through a fast-track registration the agency grants without notice as long as a developer's emissions estimates stay under 250 tons a year of any one pollutant.
  • 17 suspended construction approvals switched back on. A snapshot of the agency's portal taken November 2, the morning before the election, showed all 17 suspended. By November 13, all 17 were active again, with no explanation to the public.

The three plants are SpaceX's plant outside Brownsville, the CloudBurst plant outside San Marcos and Atlas Energy Solutions' plant in Shackelford County.

Two of them are near communities that have already said no. San Marcos was the first city in Texas to ban data centers. Brownsville passed a 90-day moratorium on November 4.

The SpaceX permit

The Brownsville plant is for Elon Musk's planned $24 billion data center, a gas-fired power plant and computing center on a 444-acre tract east of Brownsville.

According to the Levelland & Hockley County News-Press, the air permit allows up to 248 tons a year of nitrogen oxides. Public Citizen puts the exact figure at 248.86 tons, 1.14 tons under the 250-ton line that would have meant public notice, a 30-day comment period and a chance to request a hearing.

The people living next to it had already made their views clear. Cameron County commissioners voted against SpaceX's request for a tax break for the facility. "Our Brownsville community has made it clear that we vehemently oppose the SpaceX data center," Bekah Hinojosa of the South Texas Environmental Justice Network told Public Citizen.

It isn't the first time Abbott's appointees have moved for SpaceX right after an election. A draft agenda for his hand-picked parks commission put a closed-door session on selling 1,300 acres in Cameron County on its calendar for two days after the vote. Two sources told Texas Monthly the land was Boca Chica State Park and the buyer was SpaceX.

The lame-duck window

Abbott lost to Democrat Gina Hinojosa, who takes office in January. She has pledged a moratorium on data centers until lawmakers write stricter rules.

That leaves less than two months in which projects approved now can get in before the rules change. "Texans know how to read a calendar, and they see a lame-duck period when the data center industry is rushing to get in while it can," Kathryn Guerra of Public Citizen said.

The industry has been good to Abbott. A Texas Tribune analysis found he raised about $9 million from data center-related donors, and his biggest monthly haul came after he announced the pause.

What the record shows

Greg Abbott told Texas regulators to approve no data center permits until his audit was done. On November 13, ten days after he lost, his office told them they could start again. The next business day, with no public notice, they approved three gas plants big enough to power 875,000 homes, including SpaceX's, which is allowed 248 tons a year of nitrogen oxides, just under the 250-ton line for public notice. The audit's final report isn't due until December 10, and the public still hasn't seen its findings.

Source

Abbott lifts pause, data center permits move forward — Levelland & Hockley County News-Press